Update on the ongoing repair works along the A396 at Cutcombe Hill
Over the past week we have been able to stand down the planned night‑time road closures, which has reduced disruption to local residents and road users. During this time, the team has continued to make steady progress by completing the remaining elements of the scheme under daytime traffic light control. This has allowed us to keep the road open where possible, while maintaining a safe working environment for the crew.
The scheme is now approaching its final stages. However, during the excavation and reinstatement activities, some unavoidable damage occurred to the road surface. After reviewing the condition of the carriageway, it has been agreed that this is a good opportunity to carry out resurfacing. Completing this now will avoid the need for a separate return visit later in the year and will provide a smoother, more durable finish for all road users.
To deliver these surfacing works safely and efficiently, we are proposing short daytime road closures on Thursday 26th February and Friday 27th February, from 9am to 3pm on both days. These closures will give the crew the necessary working area and will prevent vehicles from travelling over freshly laid material before it has properly cured.
Once the resurfacing is complete, only minor finishing tasks and site demobilisation will need to be done, which will be carried out with minimal impact on traffic.
We appreciate the continued patience and cooperation shown by residents, local businesses and road users throughout these works. Your understanding has enabled us to progress the project effectively and safely.
Kali Martin
Assistant Highway Service Manager, Somerset Council Area – West